DCPS FY98 Capital Improvement Program
Capital Work Scheduled for Summer and Fall 98

 

Home

Bibliography

Calendar

Columns
Dorothy Brizill
Bonnie Cain
Jim Dougherty
Gary Imhoff
Phil Mendelson
Mark David Richards
Sandra Seegars

DCPSWatch

DCWatch Archives
Council Period 12
Council Period 13
Council Period 14

Election 1998
Election 2000
Election 2002

Elections
Election 2004
Election 2006

Government and People
ANC's
Anacostia Waterfront Corporation
Auditor
Boards and Com
BusRegRefCom
Campaign Finance
Chief Financial Officer
Chief Management Officer
City Council
Congress
Control Board
Corporation Counsel
Courts
DC2000
DC Agenda
Elections and Ethics
Fire Department
FOI Officers
Inspector General
Health
Housing and Community Dev.
Human Services
Legislation
Mayor's Office
Mental Health
Motor Vehicles
Neighborhood Action
National Capital Revitalization Corp.
Planning and Econ. Dev.
Planning, Office of
Police Department
Property Management
Public Advocate
Public Libraries
Public Schools
Public Service Commission
Public Works
Regional Mobility Panel
Sports and Entertainment Com.
Taxi Commission
Telephone Directory
University of DC
Water and Sewer Administration
Youth Rehabilitation Services
Zoning Commission

Issues in DC Politics

Budget issues
DC Flag
DC General, PBC
Gun issues
Health issues
Housing initiatives
Mayor’s mansion
Public Benefit Corporation
Regional Mobility
Reservation 13
Tax Rev Comm
Term limits repeal
Voting rights, statehood
Williams’s Fundraising Scandals

Links

Organizations
Appleseed Center
Cardozo Shaw Neigh.Assoc.
Committee of 100
Fed of Citizens Assocs
League of Women Voters
Parents United
Shaw Coalition

Photos

Search

What Is DCWatch?

themail archives

As presented as the April 21, 1998, public working session of the Emergency Transitional Education Board of Trustees

Capital Work Scheduled for Summer 98
Schedule as Recommended by Corps of Engineers

Repairs of Eastern SHS Windows Start: May 98 Completion: June 98
Modular Chillers (2 - Summer Schools) Start: June 98 Completion: June 98
25 Roof Replacements Start: June 98 Completion: October 98
3 Window Replacements Start: June 98 Completion: September 98
2 Asbestos Abatement Start: July 98 Completion: October 98
2 ADA Compliance Start: July 98 Completion: October 98
2 Structural Repairs Start: June 98 Completion: September 98
3 Interior Finishes Start: July 98 Completion: October 98

DCPS FY 98 Capital Improvements Program — Fall FY 98

Key Activities Time Lines Executive Summary
15 Boiler Projects in 19 Schools
  • Engineering Designs Being Completed
  • A Bid Package in Preparation
June Start – March 99 Completion As need Temporary heat will be provided by contractor(s)
6 Emergency Generators July Start – October Completion Emergency Generators will not hinder School Operations. These new generators will serve as back up power to meet Fire Code Requirements
3 Chillers
  • Designs to be completed in May by A/E Firm & Reviewed by the Army Corp.
July Start – January 99 Completion These chillers are not essential for this Summer Operations and school activities
11 Window Projects
  • 2 A/E Designs being completed by Corp.
  • 9 Window Projects in Procurement with Army Corp.
July Start – January 99 Completion

DCPS FY 98 Capital Improvements Program Challenges

  • For contracts greater than 1 million, District of Columbia's external review requirements may add six weeks to award process.
  • DCPS legal sufficiency review/tax compliance/EEO compliance/DUNS numbers assignments — 1 week
  • City Council review — 2 weeks
  • Control Board review — 2 weeks
  • FMS obligation/D.C. Controller's Office override — 1 week