Home
Bibliography
Calendar
Columns
Dorothy Brizill
Bonnie Cain
Jim Dougherty
Gary Imhoff
Phil Mendelson
Mark David Richards
Sandra Seegars
DCPSWatch
DCWatch
Archives
Council Period 12
Council Period 13
Council Period 14
Election 1998
Election 2000
Election 2002
Elections
Election
2004
Election 2006
Government and People
ANC's
Anacostia Waterfront Corporation
Auditor
Boards and Com
BusRegRefCom
Campaign Finance
Chief Financial Officer
Chief Management Officer
City Council
Congress
Control Board
Corporation Counsel
Courts
DC2000
DC Agenda
Elections and Ethics
Fire Department
FOI Officers
Inspector General
Health
Housing and Community Dev.
Human Services
Legislation
Mayor's Office
Mental Health
Motor Vehicles
Neighborhood Action
National
Capital Revitalization Corp.
Planning and Econ. Dev.
Planning, Office of
Police Department
Property Management
Public Advocate
Public Libraries
Public Schools
Public Service Commission
Public Works
Regional Mobility Panel
Sports and Entertainment Com.
Taxi Commission
Telephone Directory
University of DC
Water and Sewer Administration
Youth Rehabilitation Services
Zoning Commission
Issues in DC Politics
Budget issues
DC Flag
DC General, PBC
Gun issues
Health issues
Housing initiatives
Mayor’s mansion
Public Benefit Corporation
Regional Mobility
Reservation 13
Tax Rev Comm
Term limits repeal
Voting rights, statehood
Williams’s Fundraising Scandals
Links
Organizations
Appleseed Center
Cardozo Shaw Neigh.Assoc.
Committee of 100
Fed of Citizens Assocs
League of Women Voters
Parents United
Shaw Coalition
Photos
Search
What Is DCWatch?
themail
archives
|
As presented as the April 21, 1998, public
working session of the Emergency Transitional Education Board of TrusteesCapital Work
Scheduled for Summer 98
Schedule as Recommended by Corps of Engineers
Repairs of Eastern SHS Windows |
Start: May 98 |
Completion: June 98 |
Modular Chillers (2 - Summer Schools) |
Start: June 98 |
Completion: June 98 |
25 Roof Replacements |
Start: June 98 |
Completion: October 98 |
3 Window Replacements |
Start: June 98 |
Completion: September 98 |
2 Asbestos Abatement |
Start: July 98 |
Completion: October 98 |
2 ADA Compliance |
Start: July 98 |
Completion: October 98 |
2 Structural Repairs |
Start: June 98 |
Completion: September 98 |
3 Interior Finishes |
Start: July 98 |
Completion: October 98 |
DCPS FY 98 Capital Improvements Program Fall FY 98
Key Activities |
Time Lines |
Executive Summary |
15 Boiler Projects in 19 Schools
- Engineering Designs Being Completed
- A Bid Package in Preparation
|
June Start March 99 Completion |
As need Temporary heat will be provided by
contractor(s) |
6 Emergency Generators |
July Start October Completion |
Emergency Generators will not hinder School
Operations. These new generators will serve as back up power to meet Fire Code
Requirements |
3 Chillers
- Designs to be completed in May by A/E Firm & Reviewed by the Army Corp.
|
July Start January 99 Completion |
These chillers are not essential for this Summer
Operations and school activities |
11 Window Projects
- 2 A/E Designs being completed by Corp.
- 9 Window Projects in Procurement with Army Corp.
|
July Start January 99 Completion |
|
DCPS FY 98 Capital Improvements Program Challenges
- For contracts greater than 1 million, District of Columbia's external review
requirements may add six weeks to award process.
- DCPS legal sufficiency review/tax compliance/EEO compliance/DUNS numbers assignments
1 week
- City Council review 2 weeks
- Control Board review 2 weeks
- FMS obligation/D.C. Controller's Office override 1 week
|