Natwar Gandhi, Chief Financial Officer
Review of the PSA Dewberry Report on the cost of renovating the Martin Luther King, Jr., Library versus building a new central library
September 15, 2006

Home

Bibliography

Calendar

Columns
Dorothy Brizill
Bonnie Cain
Jim Dougherty
Gary Imhoff
Phil Mendelson
Mark David Richards
Sandra Seegars

DCPSWatch

DCWatch Archives
Council Period 12
Council Period 13
Council Period 14

Election 1998
Election 2000
Election 2002

Elections
Election 2004
Election 2006

Government and People
ANC's
Anacostia Waterfront Corporation
Auditor
Boards and Com
BusRegRefCom
Campaign Finance
Chief Financial Officer
Chief Management Officer
City Council
Congress
Control Board
Corporation Counsel
Courts
DC2000
DC Agenda
Elections and Ethics
Fire Department
FOI Officers
Inspector General
Health
Housing and Community Dev.
Human Services
Legislation
Mayor's Office
Mental Health
Motor Vehicles
Neighborhood Action
National Capital Revitalization Corp.
Planning and Econ. Dev.
Planning, Office of
Police Department
Property Management
Public Advocate
Public Libraries
Public Schools
Public Service Commission
Public Works
Regional Mobility Panel
Sports and Entertainment Com.
Taxi Commission
Telephone Directory
University of DC
Water and Sewer Administration
Youth Rehabilitation Services
Zoning Commission

Issues in DC Politics

Budget issues
DC Flag
DC General, PBC
Gun issues
Health issues
Housing initiatives
Mayor’s mansion
Public Benefit Corporation
Regional Mobility
Reservation 13
Tax Rev Comm
Term limits repeal
Voting rights, statehood
Williams’s Fundraising Scandals

Links

Organizations
Appleseed Center
Cardozo Shaw Neigh.Assoc.
Committee of 100
Fed of Citizens Assocs
League of Women Voters
Parents United
Shaw Coalition

Photos

Search

What Is DCWatch?

themail archives

Government of the Dcistrict of Columbia
Office of the Chief Financial Officer
1350 Pennsylvania Avenue, N.W., Suite 209, Washington, DC 20004 (202) 727-2476 www.dccfo.com

Natwar M Gandhi
Chief Financial Officer

SEP 15 2006

The Honorable Kathleen Patterson
Chairman of Education, Libraries, and Recreation Committee Council of the District of Columbia
1350 Pennsylvania Avenue, N.W.
Suite 107
Washington, D.C. 20004

Dear Councilmember Patterson:

This letter is in response to your request for an independent review of the "Cost-Benefit Analysis Update" by PSA-Dewberry Inc. ("PSA-Dewberry Report") that compares the potential cost of building a new central library at the old convention center site with the option of renovating the existing central library. The Office of the Chief Financial Officer ("OCFO") has reviewed the PSA-Dewberry Report and has performed an analysis of the comparative costs of building a new central library versus renovating the existing central library. Our main findings are the following:

  • The cost of building a new library is approximately the same as the cost of renovating the existing library. Either option will cost approximately $275 million.
  • Either option will cost more than the amounts estimated in the PSA-Dewberry Report.
  • The higher cost estimates will require additional financing sources.

The attached Table 1 highlights the findings. The OCFO's cost estimates for the construction of a new central library are approximately $61 million higher than the estimates in the PSADewberry Report. Over 40% of the cost differential can be attributed to the project contingency and the financing costs. The OCFO's estimates include a 10% project contingency as well as approximately $11 million for the cost of financing the project, whereas the PSA-Dewberry Report only includes a 5% contingency and no estimate for financing.

In addition, approximately 18% of the cost differential can be attributed to the soft costs of the project. The OCFO's soft cost estimates include costs related to testing, permits, fees, consultants, and legal and accounting services that were not included in the PSA-Dewberry Report. The rest of the cost differential can be attributed to the hard costs of the project. The OCFO's hard cost estimates included higher numbers in a variety of areas including remediation, excavation, structural framework, electrical and plumbing, and garage construction.

The OCFO's estimates for the soft and hard costs of renovating the existing library are only slightly higher than the estimates in the PSA-Dewberry Report. The differential between the two cost estimates is primarily due to the project contingency and the financing of the project. The OCFO's estimates include a 10% project contingency and $9 million for financing, and the PSA-Dewberry Report includes a 7% contingency and no funds for financing.

Our cost numbers include estimates for the build-out and rental of interim space in a privately owned building that are in line with the estimates in the PSA-Dewberry Report. My office also examined the possibility of using publicly-owned space during the interim period. However, we could not identify available publicly-owned space in the downtown area that would be adequate to house the library's collection on an interim basis. If the District could find adequate public space to house the library on an interim basis during the renovation of the existing library, the overall cost of the renovation option could be reduced.

Because the costs of constructing a new central library are almost identical to the costs of renovating the existing central library, we do not see a financial reason to choose one option over the other. In either case, the District will need to identify additional financing sources. My office would be happy to work with you, the Office of the Deputy Mayor for Planning and Economic Development, and the DC Public Library to structure financing options to support the higher costs of the project.

Please feel free to contact me with any questions you may have.

Table 1: Cost Comparison (in millions)

 

BUILD NEW

  RENOVATE (Lease Space)
Library OCFO Difference   Library OCFO Difference
HARD COSTS              
   Total Hard Costs $134.2 $153.4 ($19.2)   $115.5 $122.0 ($6.5)
   Escalation 35.2 41.1 (5.9)   30.3 27.9 2.4
   Total Hard Costs w/ Escalation $169.4 $194.5 ($25.1)   $145.9 $150.0 ($4.1)
SOFT COSTS              
   Total Soft Costs $34.3 $45.0 ($10.7)   $35.4 $42.0 ($6.6)
ADDITIONAL COSTS              
   Project Contingency $10.2 $24.4 ($14.2)   $12.1 $20.0 (7.9)
   Financing - 10.7 (10.7)   - 8.8 (8.8)
   Total Additional Costs $10.2 $35.1 ($24.9)   $12.1 $28.8 ($16.7)
TOTAL PROJECT BUDGET $213.9 $274.5 ($60.6)   $193.31 $220.7 ($27.4)
PRIVATE TEMPORARY SPACE              
   Private Temporary Space Buildout n/a n/a n/a   $24.3 $30.6 (6.3)
   Private Temporary Space Rent n/a n/a n/a   36.0 23.6 12.4
   Total Private Temporary Space Costs n/a n/a n/a   $60.3 $54.2 $6.1
TOTAL BUDGET PRIVATE TEMP SPACE $213.9 $274.5 ($60.6)   $253.6 $274.9 ($21.3)
COSTS NOT INCLUDED              
   New Book Collection $15.0 $15.0 $0.0   $15.0 $15.0 $0.0
   MLK Abatement w/ Escalation - $13.1 ($13.1)   -   $0.0
*Note: MLK Abatement w/ Escalation refers to the cost to abate asbestos in the current library prior to disposition.